When a generator accumulates more than 55 gallons of hazardous waste (or 1 quart of acute hazardous waste) at an SAA, the excess of 55 gallons (or the excess of 1 quart of acute hazardous waste) needs to be removed from the SAA within three days. What is

Three days means three consecutive days. It does not mean three working days or three business days. Originally, the Agency had proposed to use 72 hours as the time limit but realized that determining when 72 hours had elapsed would have required placing both the date and time of day on containers. In the final rule the Agency switched to using three days so that generators only need to date containers that hold the excess of 55 gallons of hazardous waste (or 1 quart of acute hazardous waste).